For the Faido tunnel boring machines, there is also the contractor's semi-regular weekly report (showing a progress of 110.9 resp. 73.5 m in the two tubes).

...and you get averages for the entire Faido tunnels (including weeks-long stops for vacations and maintenance) of 9.44 resp. 9.04 m/day. (So the final holing-through can be expected in the first half of 2011.)